Ukrnafta prepares for construction of two wells
![](https://drillingcontractor.org/wp-content/uploads/2024/07/Качалка-1.07.ee8dbf22f76f337eeceb878134f542d3-780x470.jpg)
Ukrnafta has started work on the construction of two oil wells that will produce more than 100 tons of oil per day. Both wells are being constructed on a turnkey basis by Energofinans LLC, a contractor selected through Prozorro. The wells will tap into productive layers of Visean deposits.
“The first well is planned as an exploratory, directional well with a design depth of 4,490 m and a forecasted flow rate of 56.6 tons per day,” Serhii Koretskyi, CEO at Ukrnafta, said. “The second well, a vertical production well, also has a design depth of 4,490 m and a forecasted initial flow rate of 47 tons per day.”
Drilling is set to start in August, with drilling equipment currently being transported and site preparations underway.