Vietsovpetro brings BK-26 platform onstream at Bach Ho field offshore Vietnam

Vietsovpetro started commercial production from the BK-26 wellhead platform at the Bach Ho (White Tiger) field in Block 09-1 offshore Vietnam. First oil came 36 days ahead of the 15 December target set by the Vietnam-Russia joint venture’s council.
The project includes the BK-26 wellhead platform and a bridge connecting it to the existing MSP-8 platform, which was modified to receive and process production from BK-26. The work also included relocating the MSP-8 to MSP-4 subsea power cable. Construction began on 29 December 2025. The jacket was installed offshore on 17 May 2026 and the topsides on 15 September.